Preface
Text Box: In The Name of God
The Compassionate The Merciful Almighty God

We are  thankful  to God that with the endeavor and efforts of the  employees of this company . we passed the year  1388  with progress and service to the people by  taking valuable and positive steps. With respect to the existing potential in the Company and also perseverance, convergence, commitment and honesty in the staff's performance and nevertheless, the proper and appropriate use  of resources (human and material), led YREC to perform its mission, more successfully as compared to the past and act with full motivations and energy, implementing significant projects which are very effective and play a vital role in the stability of National Electricity Networks, especially South East Network.

Major activities in the year 2009-2010: 
1 – Follow-ups and expediting the projects approved by the government's cabinet trip witch consists of four big projects: 
   A: Tabbas - Bafgh  400 KV line   B: Mehdiabad - Bafgh  400 KV line 
   C: Bafgh 230/400 KV Post           D: Tabbas 132/400 KV posts 
2 - Follow-ups with respect to the construction of Combined Cycle Plants of 500* 2  MW by the private sector (B.O.O) 
3 - Follow-ups  regarding Construction of Combined Cycle Power Plants with a capacity of 73 MW in Abarkouh and 43 MW in Mehriz.
4 - Completion of 12 projects transmission and sub-transmission projects with  an approximately value of 166 billion rials. 
5 – The compilation of company's strategic plan .

Major future programs in the year 2010-2011 :
1 - Continued and serious follow- ups regarding implementation of 42 transmission and sub-transmission of  projects valuing 2,450 billion rials. 
2 - Follow-ups for constructing Combined Cycle Power Plants and scattered generation.
3 - The establishment of the company's Strategic Management and continued project's of consumption management. 

As the year 2010-2011 has been named the year of "double endeavor and work"  by our great leader, we hope by the grace of God and the support of authorities and continuing cooperation of other organizations and  employees' efforts, we witness the growth and success  of Electricity industry  in all fields.                                                  


 Mohammad Hassan Sabaghzadegan                                                                                        Chairman  and Managing Director 
  

Yazd Regional Electric Co.   www.yrec.co.ir
Text Box: Comparison Summary Status of Yazd Regional Electric Company
DESCRIPTION UNIT YEAR GROWTH
2008-2009 2009-2010
Total Installed Power
Shahid Zanbagh MWH 97 97 0
Yazd Gas Power Plant MWH 120 120 0
Yazd Combined Cycle Power Plant MWH 406.8 726.8 78.7
Electric Energy Gross Generation
Shahid Zanbagh MWH 286,880 230,037 -20
Yazd Gas Power Plant MWH 421,443 318,581 -24
Yazd Combined Cycle Power Plant MWH 2,311,213 2,511,994 9
Fuel Consumption
Natural Gas Thousand M3 710,353 665,655 -6.3
Diesel Thousand lit 72,513 125,165 73
Length of transmission and sub- transmission lines
400 KV lines km-circuit 665.4 665.4 0
230 KV lines km-circuit 814.4 816.5 0.3
132 KV lines km-circuit 725.5 725.5 0
63 KV lines km-circuit 958 967 0.9
Number of transformers at transmission and sub-transmission level
400 KV transformers Device 4 4 0
230 KV transformers Device 18 19 6
132 KV transformers Device 16 16 0
63 KV transformers Device 57 60 5
Number of substations at transmission and sub-transmission level
400 KV subsstations Post 2 2 0
230 KV subsstations Post 6 6 0
132 KV subsstations Post 11 11 0
63 KV subsstations Post 26 28 8
Capacity  of  transmission  and sub-transmission substations
400 KV subsstations MVA 800 800 0
230 KV subsstations MVA 1,963 2,163 10
132 KV subsstations MVA 380 395 4
63 KV subsstations MVA 1,521.5 1,656.5 9
Man Power
Yazd Regional Electric Company Person 323 300 -7
Yazd Power Generation Management Company Person 206 204 -1
Total Person 529 504 -5